Last Updated 12/10/09
Schedules are estimates and contingent on weather, staffing, and equipment. Major changes in schedule estimates will be updated on this page. If you have a question or concern please contact the Engineering department at 781-316-3320.
Curb/Walk and Road Paving
Bartlett Ave (Wildwood to Mass Ave) - done
Work ongoing (anticipated completion second week of October) - done
Spring St (Highland Ave to Jason St)
Work ongoing (anticipated completion second week of October) - done
Road Paving
Appleton St, Old Spring St, Wall St, Highland Ave (Arlmont St to Spring St) - done
Work to begin the last week of September (anticipated completion second week of October) - done
Ridge St (Cutter Hill Rd to Crosby St) - done
Work to begin the last week of September (anticipated completion second week of October) - done
Road Regrading and Paving
Mead St (Lower Section) - done
Work ongoing (anticipated completion first week of October) - done
Clyde Terrace, Washington St, Wigwam Circle and Mountain Ave - done (except final paving of Washington to be completed Summer 2010)
Work to begin the first week of October (anticipated completion first week of November) - done
Sidewalk Construction
Appleton St (Rhinecliff St to Valentine Rd) - done
Work to take place the first Week of October - done
Granite Curb Installation
Park Ave (Small Traffic Island across from fire station) - done
Work to take place the first Week of October - done
|