Yesterday we requested J. Marchese and Son to perform a general cleanup of the area, to remove some of the heavy equipment and to re-position the remaining equipment to less conspicuous areas. We hope that this effort will provide for a less intrusive and more organized area for the long holiday weekend.
Construction Progress: updated November 23, 2011
Water Services: by-pass switch over
The installation of the new 8” water main has been completed and the installation of the individual water service connections is nearing completion; only eight (8) remain to be connected to the new water main. The Water Department is continuing to coordinate with residents to flush meters and perform the by-pass switch over for residents that have been notified of the completion of their service connections.
Road Work:
Today, Wednesday (11/23), approximately two-thirds (2/3) of the Forest Street Project has been paved with an initial binder course and a second intermediate asphalt. The last portion of the project from #307 Forest Street to the Town line is anticipated to have binder pavement in-place by December 3rd (weather dependent).
Remaining work for 2011:
Upon completion of paving MassDOT and the Arlington Engineering Division will prepare a punch-list of items for the contractor to complete prior to the onset of winter.
Work is anticipated to re-commence in the springtime with a goal of completing the remaining work including, drainage, sidewalk, curbing, landscaping and paving by August 2012.