15-57 Specs
15-57 Drawings
Pre-bid Site Visit: December 15, 2015 at 10:00 AM
Bid Results: The Aulson Co. $172,830.00
Campbell Construction Group $201,968.00
Meadows Construction Co. $227,000.00